GRASFM42 Hire Plant and Operator Checklist

This form must be completed and signed by the GRA-NETWORKS Supervisor or the Sub-contractor Supervisor prior to the plant work on site. This form needs to be returned for record to the Project Site Controller.
Details
Checklist
Has Plant being serviced and maintained on a regular basis? Are the safety checks being carried out daily?
Is Crane Safe Certification current
Does Operator have a certificate of competency or a licence to operate the plant?
Has the operator received appropriate training in regard to the operation of specific plant (read and understood the operation manual /or trained and competent in operation of all controls)?
Is a Plant Risk Assessment provided for the item of plant?
Has a pre-operational checklist been completed for this item of plant?
Has a visual check been conducted on the plant/machinery and any damage recorded?
Has operator completed site induction and attended a pre-start meeting?
Has a plant SWMS been completed and sighted?
Has operator been instructed in the site safety rules, emergency procedures and site orientation? (including relevant Safe work procedures and SWMS)?
Does the operator appear congnitive? (free from Alcohol and drug influence)?
Is the plant operating area adequately barricaded? Is the workplace area clearly marked and separated from the public area? Is there signage in place adequate to warn and direct pedestrians?
Has a Spotter been assigned during maneuvering of plant? Has a clear method of communication between the Spotter and Plant Operator been established?
Is emergency equipment compliant e.g. Fire extinguisher test/tagged?
If any of the above answers is "NO", the Plant and Operator must not commence work on the site until the problem is rectified.